"Wastewater that has been treated and filtered through the local system is actually cleaner than the natural bayou water it ultimately flows into." --Jean Simon
|
Innovative Wastewater Treatment
Crowley Facility Ranks Among Largest Systems of Its Kind
By Charles East, Jr.
Photos by David Humphreys
ASK A SOUTH LOUISIANIAN what the city of Crowley is famous for, and you'll probably be
told it's the "Rice Capital of America." But Crowley has also earned its own identity in environmental circles: the city's innovative wastewater treatment facility is one of the largest combined "artificial marshrock/reed filter" systems in the world.
This emerging technology, also known by the terms "microbial rock filter" system and "constructed wetlands," features a large pond for municipal wastewater and storm-water storage and preliminary treatment, as well as a natural filter.
The filter consists of a shallow basin filled with rock, on which plants --- in Crowley's case, southern giant bulrush are grown. The plant roots are presumed to provide additional treatment by taking some nutrients from the wastewater and by introducing oxygen into the wastewater
flow.
The Crowley facility was built at a cost of $3.76 million and funded by a construction grant through DEQ using U.S. Environmental Protection Agency (EPA) funds, as well as local monies.
The system began operation in June 1992. It is classified as innovative because it relies on technology that has not been proven fully and because it is designed for low energy consumption,
utilizing natural treatment processes and wind-driven aeration.
The cost savings on electricity and other utilities are noteworthy. Crowley's previous plant, a mechanical operation, experienced total utility costs of about $2,500 or more per month. The
average monthly utility bills for the new wastewater treatment facility have totaled only about $130.
Because the artificial marshrock/reed process practically eliminates the need for chemical or mechanical means of treatment and usually incorporates gravity flow throughout most of the system the operation and maintenance costs are substantially less than those experienced with conventional treatment processes.
Including the price of land, Crowley's new facility cost less than a new mechanical plant would have. Mayor Robert Istre and the Crowley City Council solved several problems by going to the
artificial marsh-rock/reed system: (1) They closed an old treatment plant, located in a residential area, that emitted bad odors and attracted gnats, flies, and mosquitoes. (2) They now meet more stringent discharge permit requirements for less than the cost of typical plant construction. (3)
They reduced maintenance costs for wastewater treatment. (4) The city doesn't have to process and dispose of sludge off-site; instead, solids form in a thin layer at the bottom of the treatment system pond and don't need to be removed for many years: perhaps as long as a century, according to project engineers. (5) And Crowley has an environmentally friendly facility that is
being studied for use in establishing uniform design criteria for future treatment systems.
It should be noted that artificial marsh-rock/reed filter systems of this size are relatively new
technologies and are not fully accepted by some experts in the wastewater industry. Strong opinions on both sides of the issue have demonstrated the need for further study. Nevertheless, some wastewater treatment system designers are convinced of the merits of the process and continue to design and build more systems of this kind. Crowley's treatment system includes the
following components:
An aerator in the facultative pond
|
|
A green blanket of duckweed covers the water's surface in the open marsh area (above left), while a close-up view (above right) shows the texture of the duckweed. Algae is intentionally reduced in Crowley's wastewater treatment facility, as the duckweed prevents sunlight from reaching the water; this paritaly stops photosynthesis and major oxygen production.
|
|
- TORPEDO GRASS BUFFER AREA This buffer area is about
The microbial rock filter, made of limestone.
|
seven-tenths of an acre and is intended to filter any duckweed that may spill out of the open marsh area. It also
includes two aerators to ensure adequate dissolved oxygen in the wastewater that enters
the microbial rock filter.
- MICROBIAL ROCK FILTER The
filter, covering 18 acres planted with
southern giant bulrush, is designed to
provide final "polishing" of the wastewater.
About 18 inches thick, the filter consists of
individual pieces of large limestone rock.
This layer is separated from the ground by
a liner made of polypropylene mesh.
Changing an ultraviolet bulb.
|
ULTRAVIOLET DISINFECTION
This method of disinfection was selected to
meet the permit fecal coliform bacteria
limit because it was more cost effective
than chlorination and dechlorination.
RECIRCULATION SYSTEM A single pump capable of delivering approximately one
million gallons per day was recently added at the post-aeration basin, the treatment unit
that receives water after it is disinfected. One purpose of this pumping system is to
recirculate the treated water to the facultative pond in periods of low flow. This provides
a means of constantly delivering adequate amounts of water to the artificial marsh and
rock-reed plants, even during periods of relatively dry weather. The recirculation system
also allows the operator to break up stagnant zones in the facultative pond that could
otherwise cause odor problems.
|
|
| Click for full-size photo (242K). |
The artificial marsh-rock/reed filter system is essentially a controlled natural process for the
secondary and tertiary treatment of wastewater following primary treatment in the oxidation pond, according to project engineering consultant Tim Mader of Mader-Miers Engineering, Inc. in Lafayette.
Fred Trahan, project engineer with the firm, says the system treats water in much the same way as a natural stream, in which the action of the water flowing over the rocks in the stream bed -- combined with the aquatic plants' absorption of dissolved nutrients gives the water a purity and clarity.
In fact, Crowley Wastewater Superintendent Jean Simon says the wastewater that has been treated and filtered through the local system is actually cleaner than the natural bayou water it ultimately flows into.
To arrive at that clean, filtered stage, the Crowley wastewater goes through a treatment process
lasting about 60 days, Simon explains. (See diagram) Wastewater enters the system at the inflect area and is forced hydraulically and encouraged -- through the action of aerator/mixers to move out and around a fingerlike peninsula before traveling back down toward the effluent exit. This
phase lasts a minimum of 52 days, Simon says.
After leaving the main pond, the water travels by gravity into four shallow marshes, where it remains for a minimum of three days. It then travels to the rock/reed filter area, taking about two
days (under present flows) before passing through to the ultraviolet contact chamber for disinfection. Finally, the water proceeds to the post aeration basin -- equipped with its own aerator -- before discharge into Bayou Placeman Brule. The bayou empties into the Mermentau River.
During periods of hot and dry weather,
Mader says, it is possible with the
recirculation system for the Crowley
treatment facility to function for days
without any discharge into the receiving
bayou.
"DEQ is highly appreciative of the
leadership and cooperation shown by
Mayor Istre, the City Council, and their
staff in bringing about this new system,"
says Dale Givens, Assistant Secretary for
DEQ's Office of Water Resources. "We
applaud the steps they are taking to
improve Crowley's wastewater collection
and treatment."
Local officials are justifiably proud of the
innovative system. In fact, tours of the
facility can be arranged by contacting the
City of Crowley.
Louisiana Environmentalist July - August, 1993.
|
|